Project was signed Q3, 2008. Work commenced Q1, 2009.

The cumulative project value (including variations) till date stands at AED 30 Million. The project mainly consists of fabrication, supply, finishing and erection on site of Pipe Racking, Stainless Steel Cable Tray, Gratings, Road Barriers, Handrails and various complementary metal works.

The contract includes over one thousand tons of pipe racking and more than 12,000 linear meters of stainless steel cable trays. A team of at least seven engineers/supervisors have continuously been present onsite to oversee and manage progress on the contract. QC checks are performed at both our fabrication facilities as well as onsite.

The project began with a team of 200 workers onsite and at our fabrication facility. Our workers were accommodated on site and all client HSE requirements were met. Currently, onsite staff has been reduced to less than 50 as the project is nearing completion. We have not had a single accident or injury onsite in more than one thousand days of onsite work, and have suffered a minimal number of lost time incidents, both onsite and at our facility.